The masonry stair and elevator tower are completed and the scaffolding has been taken down.

The last section of concrete footing was poured this week and the concrete piers with anchor bolts were also poured.

Underground plumbing and electrical are just about completed under the mezzanine section. This floor slab will be poured next week.